All Programs > Planning and Expansion > Regional Planning Coordination > 1-5 Corridor Regional Planning Study Team
Study Team: 1-5 Corridor Regional Planning Study Team

1-5 Corridor Regional Planning Study Team Overview

ColumbiaGrid initiated a WECC Regional Planning Project Review Process for the BPA sponsored I-5 Corridor Project in June 2007. A Regional Planning Review Group was formed to study this project. This study effort resulted in the Regional Planning Project Report that was sent to WECC on January 31 for a 30-day comment period. No comments were received on this report. On March 21 WECC notified its members that it had accepted the Regional Planning Project Review for the I-5 Corridor project. This study team has concluded its work.
 
The I-5 Corridor project is currently going through the Phase 1 Rating process via the WECC Technical Study Coordination Group.

 

Timeframe: Study Completed

Status: Inactive

Lead Staff:
Jeffrey C. Miller, P.E.  
  contact via email>

Additional Staff

Documents
03/26/2008 I-5 Corridor Regional Planning Letter (v: 1)   

-5 Corridorletter_3.14.08_.pdf   download>

 

02/01/2008 I-5 Corridor Project Regional Planning Compliance Report (v: sent)   

request access >  login >

 

01/23/2008 I-5 Draft Compliance Report (01.23.07) (v: draft)   

request access >  login >

 

12/17/2007 I-5 Corridor Reinforcement Presentation (v: 121707)   

...ia_Grid_I-5_Corridor_Dec17.pdf   download>

 

09/14/2007 I-5 Corridor Reinforcement September 5 Presentation (v: 1)   

...ia_Grid_I-5_Corridor_Sept5.ppt   download>

 

09/05/2007 I-5 Corridor Meeting Notice (9.5.07) (v: 1)   

...september-5-meeting-notice.pdf   download>

 

08/22/2007 I-5 Corridor Reinforcement Presentation (v: 1)   

...i-5_corridor_reinforcement.ppt   download>